NTPC Subsidiary Commissions 250 MW Tehri Pumped Storage Unit II

Written by: Team Angel OneUpdated on: 9 Jul 2025, 3:36 pm IST
THDC, a subsidiary of NTPC, has declared commercial operation of the 2nd 250 MW unit at Tehri PSP, taking its total installed capacity to 2,747 MW.
NTPC Subsidiary Commissions 250 MW Tehri Pumped Storage Unit II
ShareShare on 1Share on 2Share on 3Share on 4Share on 5

THDC India Limited has declared the 2nd unit (250 MW) of its Tehri Pumped Storage Project (Tehri PSP) to be in commercial operation from July 10, 2025. This unit is part of the 4x250 MW hydroelectric project located in Tehri, Uttarakhand. 

With this, the total installed and commercial capacity of the NTPC group reaches 82,836 MW 

Project Configuration

The Tehri PSP is designed with a total capacity of 1,000 MW, split across four units of 250 MW each. The project is intended to provide peaking power by storing and releasing water through reversible pump turbines.

Following the commissioning of Unit II, the total installed and commercial capacity of THDC India Limited has reached 2,747 MW. This includes the earlier commissioned projects under its portfolio.

Regulatory Disclosure

The information was communicated by THDC India Limited to the Bombay Stock Exchange (BSE) and the National Stock Exchange (NSE) through an official filing dated July 8, 2025. The declaration complies with Regulation 51(1) and Part B of Schedule III of SEBI’s Listing Regulations, 2015.

About THDC India

THDC India Limited operates as a joint venture between NTPC Limited and the Government of Uttar Pradesh. The Tehri PSP is one of its key hydroelectric infrastructure projects under development.

Read more: NTPC to Consider ₹18,000 Crore Fundraise!

NTPC Share Price Performance

As of July 9, 2025, at 10:02 AM, the NTPC share price is trading at ₹343.75, a 0.16% increase.

Conclusion

The 2nd unit of the Tehri PSP is now commercially operational, adding 250 MW to the grid. 2 more units remain to be commissioned as part of the full 1,000 MW capacity planned for the site.

Disclaimer: This blog has been written exclusively for educational purposes. The securities mentioned are only examples and not recommendations. This does not constitute a personal recommendation/investment advice. It does not aim to influence any individual or entity to make investment decisions. Recipients should conduct their own research and assessments to form an independent opinion about investment decisions. 

Investments in the securities market are subject to market risks, read all the related documents carefully before investing.

Published on: Jul 9, 2025, 10:05 AM IST

Team Angel One

Team Angel One is a group of experienced financial writers that deliver insightful articles on the stock market, IPO, economy, personal finance, commodities and related categories.

Know More

We're Live on WhatsApp! Join our channel for market insights & updates

Open Free Demat Account!

Join our 3 Cr+ happy customers

+91
Enjoy Zero Brokerage on Equity Delivery
4.4 Cr+DOWNLOADS
Enjoy ₹0 Account Opening Charges

Get the link to download the App

Get it on Google PlayDownload on the App Store
Open Free Demat Account!
Join our 3 Cr+ happy customers