Ashoka Buildcon Share Price in Focus; Receives LoI from REC Power for Sakoli Transmission Project

Ashoka Buildcon Limited has received a Letter of Intent (LoI) from REC Power Development and Consultancy Limited for a transmission project in Bhandara district, Maharashtra.
The company disclosed the LoI on August 13, 2026, through an exchange filing after submitting its bid for the project.
Transmission Project
The project involves establishing a 400/220/132 kV AIS Sakoli facility under the Tariff Based Competitive Bidding (TBCB) process. REC Power Development and Consultancy Limited is the entity awarding the contract. The company has classified the order as a domestic contract.
24-Month Completion Period
Ashoka Buildcon is required to complete the project within 24 months. After completion, the operation and maintenance period will run for 35 years, according to the details provided in the company’s filing.
Annual Transmission Charges
The filing puts the annual transmission charges at ₹1,265.37 million for 35 years. This is equivalent to about ₹126.54 crore a year. The disclosure gives the figure as the broad consideration or size of the contract.
Performance Bank Guarantee
One of the conditions of the LoI is the submission of a performance bank guarantee of ₹16.70 crore. Ashoka Buildcon has to provide the guarantee within 10 days from the date of issuance of the LoI.
Other Details
The company said the promoter, promoter group, and group companies have no applicable interest in the entity awarding the order. It also stated that the contract does not fall under related party transactions.
Read More: Hindustan Aeronautics Share Price in Focus After Q1 FY27 Earnings Results: Total Income Up 15.3% YoY!
Ashoka Buildcon Share Price Performance
As of August 14, 2026, 11:21 am, Ashoka Buildcon share price was trading at ₹112.85, a 0.37% increase from the previous closing price.
Conclusion
The LoI covers the Sakoli transmission project, with 24 months set for completion and 35 years for operation and maintenance. Annual transmission charges have been stated at ₹1,265.37 million for the 35-year period.
Disclaimer: This blog has been written exclusively for educational purposes. The securities mentioned are only examples and not recommendations. This does not constitute a personal recommendation/investment advice. It does not aim to influence any individual or entity to make investment decisions. Recipients should conduct their own research and assessments to form an independent opinion about investment decisions.
Investments in the securities market are subject to market risks, read all the related documents carefully before investing.
Take action on today’s market news - Complete your Demat Account Opening now.
Published on: Aug 14, 2026, 12:25 PM IST

Team Angel One
- Tembo Global Industries Shares in Focus; Signs MoU with Belgium’s Lachaussee SA for Advanced Ammunition Production Line
- PC Jeweller Share Price Gains Over 37% in Past 3 Days: Here's Why?
- Shyam Metalics Share Price in Focus; Reports August 2026 Sales Performance
- RBL Bank Share Price in Focus as Board Approves Euro Medium Term Note Programme
- Brightcom Group Share Price Surges 7%; Confirmed for Inclusion in FTSE Global Equity Index Series