ACME Solar Share Price Rises Over 4%; Commissions Phase-I of Rajasthan BESS Project

Written by: Team Angel OneUpdated on: 15 Sept 2026, 6:38 pm IST
ACME Solar commissions 53.63 MW/300 MWh of BESS capacity in Rajasthan as part of its 300 MW/1,581 MWh FDRE project.
ACME Solar Share Price Rises Over
Share

ACME Solar Holdings Limited has commissioned Phase-I of the Battery Energy Storage Systems (BESS) component of its Rajasthan project, as per an exchange filing dated September 14, 2026.  

The company completed the commissioning on September 14, 2026, through its wholly-owned subsidiary, ACME Greentech Seventh Private Limited. 

53.63 MW/300 MWh Added 

The commissioned phase has a capacity of 53.63 MW/300 MWh. It forms part of a 300 MW/1,581 MWh Firm and Dispatchable Renewable Energy (FDRE) project located at Village Kelan, Tehsil Chhatargarh, District Bikaner, Rajasthan. 

Renewable Energy Work Continues 

The battery storage facility is the only component of the project commissioned so far. The renewable energy generation component of the project remains under development, according to ACME Solar. 

The company has not provided a completion timeline for the renewable energy generation component in its disclosure. The commissioned BESS capacity therefore represents part of the wider 300 MW/1,581 MWh project. 

COD on September 16, 2026 

The commercial operation date (COD) for the commissioned BESS component is scheduled for September 16, 2026. The date comes two days after the company completed the commissioning of Phase-I. 

Project Structure 

ACME Solar is undertaking the BESS project through ACME Greentech Seventh Private Limited, its wholly-owned subsidiary. The storage facility is being developed as part of the larger FDRE project in Bikaner district. 

Read More: HDFC Bank Share Price Surges; Two Names Submitted to RBI for MD and CEO Role! 

ACME Solar Holdings Share Price Performance  

As of September 15, 2026, at 12:42 pm, ACME Solar Holdings share price was trading at ₹419.40, up 4.25% from the previous closing price. 

Conclusion 

ACME Solar has commissioned the first 53.63 MW/300 MWh phase of its 300 MW/1,581 MWh FDRE project in Rajasthan. The renewable energy component is still under development, while the commissioned BESS is due to begin commercial operations on September 16, 2026. 

Disclaimer: This blog has been written exclusively for educational purposes. The securities mentioned are only examples and not recommendations. This does not constitute a personal recommendation/investment advice. It does not aim to influence any individual or entity to make investment decisions. Recipients should conduct their own research and assessments to form an independent opinion about investment decisions.  

Investments in the securities market are subject to market risks, read all the related documents carefully before investing. 

Published on: Sep 15, 2026, 1:08 PM IST

Team Angel One

Team Angel One is a group of experienced financial writers that deliver insightful articles on the stock market, IPO, economy, personal finance, commodities and related categories.

Know More
Enjoy Zero Brokerage on Equity Delivery
10 Cr+DOWNLOADS

Enjoy ₹0 Account Opening Charges

Get the link to download the App

Scan this QR code to download the app
Get it on Google PlayDownload on the App Store

Open Free Demat Account!

Join our 3.8 Cr+ happy customers
+91